← Back to All Categories

Construction Knowledge Center

Explore our verified library of Construction transactions. Every entry is reviewed for IFRS compliance and real-world accuracy by our technical accounting team.

Construction

How to Record Retention Receivables on Construction Progress Billings

How to account for the percentage of payment withheld by a client until project completion.

Read Analysis
Construction

How to Apply Manufacturing/Construction Overhead to Work-in-Process

Allocating indirect production costs to Work-in-Process (WIP) based on a predetermined rate.

Read Analysis
Construction

How to Record the Sale of Manufacturing/Construction Scrap

Recording the miscellaneous income from selling byproduct or waste materials from production.

Read Analysis
Construction

How to Transfer WIP to Finished Goods (Cost of Goods Manufactured)

Recording the completion of production and moving costs from Work-in-Process to Finished Goods inventory.

Read Analysis
Construction

How to Record the Sale of Construction Site Scrap Material

Recording revenue from selling excess rebar or copper scrap from a job site.

Read Analysis
Construction

How to Record a Project Mobilization Advance Payment

Receiving an upfront payment from a client to start a construction project.

Read Analysis
Construction

How to Capitalize Interest on a Construction Loan (IAS 23)

Adding the interest cost of a project loan to the cost of the building being constructed (IAS 23).

Read Analysis
Construction

How to Record Purchase Price Variance (PPV) in Standard Costing

Recording the difference between the standard cost of a material and the actual price paid.

Read Analysis
Construction

How to Record Retention Payable to a Subcontractor

Withholding a percentage of a subcontractor's payment as a guarantee for their work quality.

Read Analysis
Construction

How to Capitalize Borrowing Costs on Project Loans (IAS 23)

Adding interest costs to the value of a 'qualifying asset' during its construction period (IAS 23).

Read Analysis
Construction

How to Provision for an Expected Loss on an Onerous Construction Contract

Recording an immediate loss when it becomes clear that the total cost of a construction project will exceed the total revenue.

Read Analysis
Construction

How to Record Performance Bond and Insurance Premiums

Paying for a bank guarantee or insurance bond that guarantees the client the project will be completed.

Read Analysis
Construction

How to Record Contract Change Orders (Variation Orders)

Adjusting the contract value and recognizing revenue when a client requests and approves additional work mid-project.

Read Analysis
Construction

How to Amortize a Mobilization Advance via Progress Billings

Reducing the mobilization advance liability as work progresses and the advance is recovered through deductions on progress billings.

Read Analysis
Construction

How to Record a Bid Bond / Tender Guarantee Cash Margin

Recording the cash margin paid to the bank to issue a bid bond when submitting a tender.

Read Analysis
Construction

How to Record a Bid Bond Release Post-Award

Releasing the bid bond margin back to the current account after the tender result.

Read Analysis
Construction

How to Record Advance Payment Guarantee (APG) Bank Fees

Recording the bank's annual commission for issuing an Advance Payment Guarantee (APG) on behalf of the contractor.

Read Analysis
Construction

How to Record a Letter of Guarantee (LG) Cash Margin Deposit

Recording cash blocked by the bank as collateral for issuing a performance or advance payment guarantee.

Read Analysis
Construction

How to Amortize Contractor All-Risk (CAR) Insurance Premiums

Paying the annual Contractor All-Risk insurance premium for a construction project.

Read Analysis
Construction

How to Capitalize Site Establishment and Mobilization Costs

Capitalizing the initial cost of setting up the construction site — fencing, signage, temporary roads, and site offices.

Read Analysis
Construction

How to Record a Progress Billing Invoice to the Client

Issuing a monthly progress certificate invoice to the client based on work completed.

Read Analysis
Construction

How to Recognize Construction Revenue via Percentage of Completion (POC)

Recognizing revenue based on the percentage of the project physically completed at month-end.

Read Analysis
Construction

How to Record Over-Billings (Billings in Excess of Costs and Estimated Earnings)

Recording the liability when the amount invoiced to the client exceeds the revenue actually earned based on completion.

Read Analysis
Construction

How to Record Under-Billings (Costs and Estimated Earnings in Excess of Billings)

Recording the asset when revenue earned based on completion exceeds the amount invoiced to date.

Read Analysis
Construction

How to Record the Release of Retention Receivables

Collecting the withheld retention amount from the client after achieving practical completion and the defects period ending.

Read Analysis
Construction

How to Accrue Revenue for Construction Claims and Extensions

Accruing revenue for a claim submitted to the client for additional costs caused by employer-risk events (e.g., design changes, delays).

Read Analysis
Construction

How to Handle Disputed Variation Orders (Contingent Revenue)

Recording a variation order submitted to the client that is under dispute and not yet approved.

Read Analysis
Construction

How to Record Price Escalation Clause Revenue Adjustments

Increasing the contract value due to a contractual price escalation clause triggered by rising material or fuel costs.

Read Analysis
Construction

How to Record Milestone Payments Received from Clients

Collecting a payment linked to achieving a specific project milestone (e.g., structural completion).

Read Analysis
Construction

How to Record the Final Account Settlement on Project Closeout

Recording the agreed final contract value after all variations, claims, and adjustments are settled.

Read Analysis
Construction

How to Record Cash Purchases for Site Materials

Buying construction materials (steel, cement, blocks) with cash for immediate site use.

Read Analysis
Construction

How to Transfer Material from Central Store to Site WIP

Moving materials from the central warehouse to a specific project site.

Read Analysis
Construction

How to Record Surplus Material Returned to Central Stores

Returning unused materials from a project site back to the central warehouse.

Read Analysis
Construction

How to Write Off Abnormal Material Wastage on Site

Writing off materials damaged or wasted beyond acceptable norms on the construction site.

Read Analysis
Construction

How to Capitalize Import Duties on Construction Materials

Capitalizing customs duties paid on imported structural steel or specialist equipment into the material cost.

Read Analysis
Construction

How to Record Fuel and Consumables for Plant Machinery

Recording diesel and lubricants used by excavators, cranes, and generators on site.

Read Analysis
Construction

How to Record Advance Payments to Material Suppliers

Paying a cement or rebar supplier in advance to secure materials at an agreed price.

Read Analysis
Construction

How to Offset Supplier Advances Against Material Deliveries

Clearing the advance when the supplier delivers materials and invoices the project.

Read Analysis
Construction

How to Allocate Gross Wages for Site Workers to WIP

Recording the gross wages for all site-based staff — foremen, masons, carpenters, and laborers.

Read Analysis
Construction

How to Record Employer Social Security Contributions for Site Workers

Recording the employer's SSC obligation for site workers as a direct project cost.

Read Analysis
Construction

How to Accrue Overtime Wages for Site Construction Workers

Accruing overtime wages for site workers during an accelerated construction phase.

Read Analysis
Construction

How to Provision for End-of-Service Benefits (EOSB) for Site Staff

Accruing the end-of-service benefit for long-term site employees as required by local labor law.

Read Analysis
Construction

How to Record Worker Accommodation and Camp Costs

Recording the cost of housing, meals, and transportation provided to workers at a remote construction site.

Read Analysis
Construction

How to Capitalize Safety Gear and PPE for Site Workers

Purchasing hard hats, safety boots, harnesses, and hi-vis vests for all site personnel.

Read Analysis
Construction

How to Capitalize Foreign Worker Visa and Mobilization Costs

Recording the visa fees, medical exams, and flight costs to mobilize foreign laborers to the site.

Read Analysis
Construction

How to Record Labour-Only Subcontractor Invoices

Recording the cost of a gang of workers supplied by a labour-only subcontractor (materials are provided by the main contractor).

Read Analysis
Construction

How to Allocate Staff Transport Costs to Project WIP

Recording the cost of daily bus transport for workers between accommodation and the construction site.

Read Analysis
Construction

How to Record Indirect Labor for Site Engineers and Supervisors

Recording the salary costs of site managers, quantity surveyors, and engineers who supervise multiple activities.

Read Analysis
Construction

How to Accrue Subcontractor Costs Before Invoice Receipt

Accruing the cost of work completed by a specialist subcontractor before their official tax invoice is received.

Read Analysis
Construction

How to Record an Advance Payment to a Subcontractor

Paying a specialist subcontractor an advance to mobilize and procure materials.

Read Analysis
Construction

How to Amortize/Recover a Subcontractor Advance

Deducting the subcontractor advance from a progress payment certificate as work is completed.

Read Analysis
Construction

How to Release Retention Payable to a Subcontractor

Releasing the retained amount to a subcontractor after their portion of works is complete and the defects period passes.

Read Analysis
Construction

How to Record a Back-Charge Against a Subcontractor

Deducting costs from a subcontractor's payment for remedial work or damage they caused.

Read Analysis
Construction

How to Record Subcontractor Termination and Demobilization Costs

Recording costs associated with terminating a non-performing subcontractor mid-contract.

Read Analysis
Construction

How to Deduct Withholding Tax from Subcontractor Payments

Deducting withholding tax from a domestic subcontractor's payment as required by local tax law.

Read Analysis
Construction

How to Settle a Subcontractor Final Account

Recording the agreed final payment to a subcontractor after all work, variations, and disputes are resolved.

Read Analysis
Construction

How to Record Specialist Consultant Fees (Structural/MEP)

Paying a structural engineer or MEP consultant for specialist design and supervision services.

Read Analysis
Construction

How to Capitalize the Purchase of Owned Plant and Equipment

Buying a construction excavator or concrete mixer for use across multiple projects.

Read Analysis
Construction

How to Allocate Plant Depreciation to Project WIP

Charging a project with its share of plant depreciation based on machine hours used.

Read Analysis
Construction

How to Record Plant Hire and Equipment Rental

Recording the weekly rental of an excavator or tower crane from a plant hire company.

Read Analysis
Construction

How to Record Tower Crane Monthly Hire Costs

Recording the monthly hire charge for a tower crane on a multi-storey building project.

Read Analysis
Construction

How to Record Scaffolding Hire Expenses

Recording the monthly rental of scaffolding system for the building façade works.

Read Analysis
Construction

How to Expense Small Tools and Site Consumables

Purchasing hand tools, drill bits, saw blades, and other consumables for site use.

Read Analysis
Construction

How to Capitalize Site Office and Temporary Building Costs

Recording the cost of portable site offices, cabins, and site-specific facilities.

Read Analysis
Construction

How to Record Site Utilities (Electricity and Water)

Paying for temporary electricity supply and water connection to the construction site.

Read Analysis
Construction

How to Record Site Security and Guard Services

Monthly cost of a contracted security company protecting the construction site from theft and unauthorized access.

Read Analysis
Construction

How to Record Plant Maintenance and Repair Costs

Recording the cost of repairing a breakdown of company-owned plant machinery on site.

Read Analysis
Construction

How to Process Plant Cost Transfers Between Projects

Moving an owned excavator from Project A to Project B mid-contract.

Read Analysis
Construction

How to Recharge Head Office Overheads to Projects

Allocating a portion of head office running costs (salaries, rent, IT) to each active project.

Read Analysis
Construction

How to Close Over-Applied Project Overhead at Year-End

Adjusting at year-end when the overhead absorbed into projects exceeds actual overhead incurred.

Read Analysis
Construction

How to Close Under-Applied Project Overhead at Year-End

Adjusting at year-end when actual overhead exceeded the amount absorbed into project costs.

Read Analysis
Construction

How to Write Down WIP for an Onerous Construction Contract

Reducing the WIP balance when a project is confirmed as loss-making and the WIP value exceeds recoverable amount.

Read Analysis
Construction

How to Transfer WIP to Cost of Sales on Project Close-Out

Transferring all remaining WIP costs to Cost of Sales upon project completion and final revenue recognition.

Read Analysis
Construction

How to Accrue a Provision for Defects Liability

Accruing the estimated cost of remedying defects during the defects liability period.

Read Analysis
Construction

How to Settle Defect and Warranty Claims Against Provision

Using the defects provision to pay for remedial work on a completed project during the warranty period.

Read Analysis
Construction

How to Record a Project Finance Loan Drawdown

Drawing down a tranche of a project finance loan to fund construction activities.

Read Analysis
Construction

How to Record Construction Loan Repayments (Principal and Interest)

Making a monthly repayment on the project finance loan after the construction phase.

Read Analysis
Construction

How to Open a Documentary Letter of Credit for Imported Materials

Opening a documentary letter of credit with the bank to import specialist materials from abroad.

Read Analysis
Construction

How to Settle an L/C Upon Material Delivery

Releasing the L/C and recording the materials when the supplier's shipping documents are presented.

Read Analysis
Construction

How to Record a Retention Bond in Lieu of Cash Deductions

Recording a bank guarantee provided to the client instead of withholding cash retention.

Read Analysis
Construction

How to Record the Factoring of a Progress Invoice

Selling a certified progress invoice to a factoring company to receive immediate cash.

Read Analysis
Construction

How to Record Output VAT on Construction Progress Billings

Charging VAT on a progress certificate raised to a client.

Read Analysis
Construction

How to Record Input VAT on Material Purchases

Recording recoverable VAT on material purchases from VAT-registered suppliers.

Read Analysis
Construction

How to Remit Withholding Tax to the Tax Authority

Paying accumulated withholding taxes deducted from subcontractors to the tax authority.

Read Analysis
Construction

How to Accrue a Corporate Income Tax Provision at Year-End

Accruing the estimated income tax on the construction company's annual taxable profit.

Read Analysis
Construction

How to Accrue Zakat on WIP and Contract Assets (Saudi Arabia)

Accruing Zakat on the construction company's Zakatable base including WIP and net working capital.

Read Analysis
Construction

How to Capitalize Import Duties on Heavy Plant and Machinery

Capitalizing customs duties on imported construction equipment (e.g., excavator, tower crane).

Read Analysis
Construction

How to Capitalize Municipality Building Levies and Permits

Paying a government levy or permit fee charged on the construction of new buildings.

Read Analysis
Construction

How to Record the Sale of Surplus Project Materials

Selling leftover materials (sand, aggregate, blocks) at project close-out to another contractor.

Read Analysis
Construction

How to Record the Disposal of Plant at Project End

Selling or writing off site plant (generators, site huts) at the end of a construction project.

Read Analysis
Construction

How to Record Liquidated Damages Paid to a Client

Recording the penalty paid to the client for failing to achieve practical completion by the contractual date.

Read Analysis
Construction

How to Record Repair Costs During the Defects Liability Period

Recording the actual cost of remedying a structural crack or defect identified during the defects liability period.

Read Analysis
Construction

How to Record an Initial Investment in a Construction Joint Venture

Recording the cash contribution to a construction joint venture (JV) formed to bid and execute a large project.

Read Analysis
Construction

How to Recognize Profit Share from a Construction Joint Venture

Recording the proportional share of a joint venture project's net income.

Read Analysis
Construction

How to Record an Intercompany Loan to a Project SPV

The parent construction company lending funds to a Special Purpose Vehicle set up for a specific project.

Read Analysis
Construction

How to Accrue Revenue for Extension of Time (EOT) Prolongation Claims

Accruing the additional prolongation costs associated with an extension of time granted by the client.

Read Analysis
Construction

How to Record Monthly Preliminary & General (P&G) Costs

Recording the time-related preliminary costs that run monthly throughout the project (management, security, utilities).

Read Analysis
Construction

How to Record Payments to Nominated Suppliers

Paying a supplier nominated by the client directly, in accordance with the main contract.

Read Analysis
Construction

How to Reclassify a Contract Asset to Trade Receivables

Moving an unbilled contract asset to a trade receivable once the progress certificate is formally issued.

Read Analysis
Construction

How to Record an Expected Credit Loss (ECL) on Construction Receivables

Provisioning for potential non-collection of certified progress invoices from a financially stressed client.

Read Analysis
Construction

How to Record an Approved Variation Order (Cost and Revenue)

Recording both the additional revenue and the direct cost for a formally approved variation order.

Read Analysis

Need a specific Construction entry?

Our team is constantly updating the hub. If you can't find what you need, suggest a new entry below.

Contact Expert