How to Record Stop Work Order Costs

Accounting for costs incurred during a period when the government issues a formal stop-work order under FAR 52.242-15.

Account NameTypeDebit ($)Credit ($)
Direct Contract Costs - Idle/Stop WorkDebit15,000.00-
Accrued Salaries and BenefitsCredit-15,000.00

💡 Accountant's Note

When a stop-work order is issued, costs should be segregated to facilitate the eventual Request for Equitable Adjustment (REA) for the period of performance delay.

Practitioner & Systems Framework

💻 ERP Architecture

Set up a unique sub-project or work package code in the ERP to capture all stop-work related charges.

⚠️ Audit Flags

Sudden spikes in idle labor charging; DCAA scrutiny of labor floor checks during stop-work periods.

📄 Required Documentation

Formal Stop-Work Order notice from the Contracting Officer (CO) and timecards specifically coded to the delay.

Did you find the exact entry you were looking for?

Automate this entry with the JEH Accounting Suite

Stop doing manual entry. Our VBA-powered ERP automatically generates your ledgers, Trial Balance, and Financial Statements.

No Subscriptions. Own your data.

QA

Expert Analysis by Qusai Ahmad

General Accountant Supervisor & IFRS Specialist

Specialized in SAP GUI automation and Middle Eastern tax compliance. Building digital tools for the next generation of finance leaders.

LinkedIn Profile

Discussion & Community Questions

Loading comments...

Leave a comment (No sign-up required)